Markedets billigste bøger
Levering: 1 - 2 hverdage

Implementation of Line of Balance in bridge project

Implementation of Line of Balance in bridge projectaf Amit Sharma
Bag om Implementation of Line of Balance in bridge project

Line of Balance (LOB) is a management control process for collecting, measuring and presenting facts relating to time all measured against a specific plan. It shows the process, status, background, timing and phasing of the project activities, thus providing management with measuring tools that help to Comparing actual progress with a formal objective plan and examining only the deviations from established plans, and gauging their degree of severity with respect to the remainder of the project. The LOB itself is a graphic device that enables a manager to see at a single glance which activities of an operation are ¿in balance¿ ¿ i.e., whether those which should have been completed at the time of the review actually are completed and whether any activities scheduled for future completion are lagging behind schedule. CPM is continuously used in India for network analysis and finding critical path, Problem is taken as challenge to introduce and the new technique named linear scheduling which is proved better than CPM for repetitive construction works.

Vis mere
  • Sprog:
  • Engelsk
  • ISBN:
  • 9783659807428
  • Indbinding:
  • Paperback
  • Sideantal:
  • 60
  • Udgivet:
  • 19. oktober 2018
  • Størrelse:
  • 150x4x220 mm.
  • Vægt:
  • 107 g.
Leveringstid: 1-2 uger
Forventet levering: 15. januar 2025
Forlænget returret til d. 31. januar 2025
  •  

    Kan ikke leveres inden jul.
    Køb nu og print et gavebevis

Beskrivelse af Implementation of Line of Balance in bridge project

Line of Balance (LOB) is a management control process for collecting, measuring and presenting facts relating to time all measured against a specific plan. It shows the process, status, background, timing and phasing of the project activities, thus providing management with measuring tools that help to Comparing actual progress with a formal objective plan and examining only the deviations from established plans, and gauging their degree of severity with respect to the remainder of the project. The LOB itself is a graphic device that enables a manager to see at a single glance which activities of an operation are ¿in balance¿ ¿ i.e., whether those which should have been completed at the time of the review actually are completed and whether any activities scheduled for future completion are lagging behind schedule. CPM is continuously used in India for network analysis and finding critical path, Problem is taken as challenge to introduce and the new technique named linear scheduling which is proved better than CPM for repetitive construction works.

Brugerbedømmelser af Implementation of Line of Balance in bridge project



Gør som tusindvis af andre bogelskere

Tilmeld dig nyhedsbrevet og få gode tilbud og inspiration til din næste læsning.